Site 1, barangay Agujo in Daanbantayan:
The construction of the 74 houses and the Multi-Purpose Center have been completed. The site now needs site development (concrete roads and sidewalks, drainage and water distribution system etc) for families to be able to move in.
FP-UA will be fundraising the P 3,300,000 needed to complete the site development of Site 1 in order to turn over the village to the beneficiary families as soon as possible.
Site 2, barangay Paypay in Daanbantayan:
The construction on Site 2 is well under way with 98 houses (out of 128) currently being built, and the site development 80% complete. The construction of the multi-purpose center and the clinic is expected to start this coming month. This site should be ready for turnover by June this year.
Site 3, barangay Cayang in Bogo:
The location for Site 3 has already been selected. This site will comprise 100 houses, built on the same Hyperbolic Paraboloid house design as on Site 1, as well as a multi-purpose center.
FP-UA still needs to fundraise 26M pesos in order to cover the cost of 50 homes as well as the cost of site development for this site.
If you would like to contribute to one of our projects, please don’t hesitate to contact us at coordination@fpua.ph